Free Concrete Calculator

Work out how much concrete you need for a slab, footing or column: volume in m³, weight, and a hand-mix bag estimate.

Enter the length, width and depth of your pour to get concrete volume in cubic metres, weight in tonnes, and a rough cement/ballast bag count for hand-mixing. Adds a waste allowance and flags when ready-mix is the better option. UK metric units throughout.

Longest side of the pour (plan length)

Unit: m.

For a trench footing, use trench width; for a column, use diameter as width

Unit: m.

Typical shed base 100mm; driveway often 150mm

Unit: mm.

Same L×W×D maths; label only. Helps match your job

Spill, uneven ground and over-order margin

Unit: %.

Results

Fill in the details and select Calculate to see your figures.

Win more of the jobs you quote.

Tradehand gives your trade business a whole office team without hiring anyone: it answers every enquiry, sends your quotes the same day and chases them until they land. There is no monthly fee. Tradehand takes 5% of an invoice, and only when the customer actually pays you, so a quiet month costs you nothing.

Get a free demo

How to use the Concrete Calculator

  1. 1Measure the plan length and width of the pour in metres.
  2. 2Enter depth in millimetres (100mm is common for light slabs).
  3. 3Pick the pour type that matches your job. The maths is the same L×W×D.
  4. 4Leave waste at 10% unless the ground is very uneven (use more) or the pour is tightly shuttered (use less).
  5. 5Read volume and weight for a ready-mix order, or cement bags + ballast for a hand mix.

How to work it out yourself

Concrete volume is length × width × depth, with depth converted from millimetres to metres, then a waste percentage on top.

volume (m³) = length × width × (depth ÷ 1000) × (1 + waste%) → round up to 0.1 m³
  1. 4m × 3m slab at 100mm: 4 × 3 × 0.10 = 1.2 m³.
  2. With 10% waste: 1.2 × 1.10 = 1.32 → round up to 1.4 m³.
  3. Weight ≈ 1.4 × 2.4 = 3.4 tonnes.
  4. Hand-mix cement ≈ 1.4 × 12 = 17 bags of 25kg; ballast ≈ 1.4 × 1.9 ≈ 2.7 tonnes.

Densities and C20 1:2:4 mix ratios are guidance only. Confirm mix grade (C20 general, C25 foundations) with your supplier or structural spec.

Typical UK benchmarks

100mm slab per m²0.10 m³ concrete per m² at 100mm depth
Concrete density≈2400 kg/m³ typical reinforced concrete
Shed base depthTypical garden shed/base slab 100mm

Disclaimer

This tool gives an estimate for general guidance only, based on typical UK figures and the details you enter. It is not a formal quote, survey, or professional advice. Always confirm with a qualified tradesperson before relying on any figure, as regional prices, site conditions, and current standards vary.

You do the job, Tradehand handles everything around it.

Tradehand sends the quotes, chases the invoices, books the work and keeps your customers updated, for no monthly fee and 5% of an invoice only once the customer has paid. One office hire costs about £25,000 a year, whether the invoices land or not.

Source: Office manager salary, National Careers Service

Get a free demo

Frequently asked questions

How much concrete do I need for a shed base?

A 3m × 2m shed base at 100mm needs about 0.6 m³ before waste, or ~0.7 m³ with 10% waste. That is roughly 1.7 tonnes. Most DIY shed bases are bagged concrete or a small ready-mix order.

What depth of concrete for a patio or path?

Light garden paths and patios are often 75–100mm on a compacted sub-base. Driveways and vehicle areas are typically 150mm or more, and foundations follow the structural design: never guess load-bearing depths.

When should I order ready-mix instead of bags?

Under about 1 m³, bagged or hand-mixed is usually practical. Over 1 m³, ready-mix by the cubic metre is faster, more consistent and often cheaper once you count labour and mixer hire.

How many 25kg bags of cement per m³?

For a standard C20 1:2:4 mix you need about 12 bags of 25kg cement per cubic metre (roughly 300 kg of cement), plus about 1.9 tonnes of ballast. Published mix tables put a 1:2:4 C20 mix at 285–320 kg of cement per m³, and BS 8500 sets a floor of 220 kg/m³ even for the weakest general-purpose grade, so treat anything near half that as a mis-order. Always check the bag/mix instructions for the grade you need.

Should I add a waste allowance?

Yes. 5–10% is normal for a well-shuttered slab; use up to 15–20% on uneven ground, trenches or first-time pours. Running short mid-pour is worse than a little left over.