Not because of the charger alone: it depends whether the whole house's demand, charger included, fits the supply you have.

Low

Blake FolgadoUpdated

What's happening?

Whether a charger needs three phase depends on the whole house, not the charger alone. Electricity North West's EV guidance sets out the case: if you have a single-phase supply rated between 60A and 100A and, after your electrician's maximum demand calculation, you need more than 100A, you apply to upgrade to three phase. That is a chargeable service from the network operator, not something the installer can do on the day. A standard three-phase connection from Electricity North West gives 60kVA, which is 80A per phase. Other network operators publish their own terms. So the order is: calculate the demand with everything on, see whether it fits the supply you have, and only then apply.

What usually causes it?

  • A large house with electric heating or a heat pump as well as the charger
  • Total demand that comes out above the supply after the maximum demand calculation
  • Two or more chargers on one supply
  • A workshop or business running off the same supply
  • An installer saying three phase is needed without showing the calculation
  • A supply that is already three phase, so no upgrade is needed

Is it dangerous?

No. It is a cost and planning question rather than a safety one. The risk is applying for an upgrade the house did not need, or fitting a charger on a supply that cannot carry it.

Can I fix it myself?

No. You can ask your network operator or your electrician which supply you have, and you can ask the electrician to show the maximum demand calculation before you apply for anything. Do not open the cut-out or the meter.

When should you call an electrician?

Before you order a charger or apply to the network operator. Ask for the maximum demand calculation, and ask whether a load management scheme would keep the house within its existing supply.

What will the electrician actually do?

  • Identify the existing supply, cut-out and meter arrangements
  • Work out the house's maximum demand with the charger and any other large loads
  • Say whether the supply is enough, whether load management would keep it enough, or whether an upgrade is needed
  • Complete the notification or application to the network operator for the charger or the supply upgrade
  • Fit the charger and any consumer unit changes it needs once the supply is settled
  • Test and certify the installation

Who fixes this

What it usually costs

Questions people ask

Do I need a 3 phase supply for an EV charger?

Not because of the charger alone. Electricity North West's guidance says you apply to upgrade to three phase when you have a single-phase supply rated 60A to 100A and your maximum demand calculation comes out above 100A.

How do I know if I have a three phase supply at home?

Your electrician can tell from the cut-out and meter, and your network operator holds the record for your address. Ask before you pay for anything that assumes one or the other.

Who does a three phase upgrade, and who pays?

The network operator does the upgrade, and it is a chargeable service. You apply to them, they quote, and the quote is theirs, not your installer's.

Can load management avoid a three phase upgrade?

Sometimes. Electricity North West's EV application guidance says load management schemes are used to reduce the size of connection required, so ask the electrician whether one would keep the house within its existing supply.

Sources & References

  1. Electricity North West: three phase power connection
  2. Electricity North West: connecting a single EV charge point
  3. IET: Code of Practice for Electric Vehicle Charging Equipment Installation